When sheathing an exterior wall, where should the sheathing begin for a wall that runs short of the exterior?

  1. Flush with the end of the wall at the beginning end.

  2. Flush with the end of the wall only at the beginning end.

  3. Hanging over the wall one stud thickness at the beginning end.

  4. Hanging over the wall one exterior wall thickness at the beginning end.

The correct answer is: Hanging over the wall one exterior wall thickness at the beginning end.

The sheathing should be hanging over the wall by one exterior wall thickness at the beginning end. This is because the sheathing serves as a protective layer for the wall and should extend beyond the edge of the wall to prevent any water or moisture from entering. Option A would leave the end of the wall exposed and vulnerable to damage. Option B would not provide enough coverage for the wall. Option C would cause the sheathing to hang too far over the edge, potentially causing issues with siding or other exterior finishes. Therefore, option D is the best choice to ensure proper protection for the wall.